MPCALA targets full CALAX opening by 2025, Governor's Drive Interchange 40% done
MPCALA Holdings, a unit of Metro Pacific Tollways Corp., remains committed to opening the full stretch of the Cavite-Laguna Expressway (CALAX) by 2025.
The Governor's Drive Interchange, the longest segment of CALAX, is now 40% complete and expected to open in the second half of this year.
Once completed, the 8.64-kilometer Governor's Drive Interchange will connect Aguinaldo Highway in Silang with other major roads in Cavite, easing traffic congestion.
Construction of the remaining sections of CALAX is also progressing; Subsection 1 (Kawit Interchange) is about 31% complete and Subsection 2 (Open Canal Interchange) has reached 21.9% completion.
CALAX, a 45-kilometer four-lane expressway with eight interchanges, is expected to serve at least 95,000 motorists daily once fully operational.